1. Purpose

This Agreement defines the terms, responsibilities, and technical requirements for the delivery, installation, and commissioning of UmproTech hydraulic press brake systems at the client's facility in the United States.

2. Scope of Work

UmproTech technicians will:

  • Assemble, align, and level the press brake on the client's site.
  • Connect electrical and hydraulic systems.
  • Perform oil fill, pressure calibration, and crowning verification.
  • Calibrate backgauge axes and Delem controller functions.
  • Conduct operational testing and operator training.

3. Client Responsibilities

The Client must:

Prepare the installation area:

  • Clear and level concrete floor (min. 8 in thick for 200T+ machines).
  • Sufficient access for forklifts or cranes (rated ≥ machine weight).
  • Provide rigging services to move and position the press brake.

Ensure correct electrical supply:

  • Proper voltage and amperage available before arrival (see table below).
  • Grounding and main disconnect within 10 ft of the machine.
  • Certified electrician available for final connection.

Provide hydraulic oil and auxiliary materials:

  • ISO VG46 hydraulic oil — quantity according to the machine manual.
  • Clean rags, funnels, and oil containers prepared.

Provide compressed air:

  • Clean, dry air at 100–115 psi (0.7–0.8 MPa).

Ensure personnel and safety readiness:

  • At least one operator available for training.
  • PPE available (gloves, goggles, steel-toe boots).
  • No unauthorized access during installation.

4. Electrical & Power Requirements

Model / Capacity Voltage Breaker Amperage Notes
HBM 90/2500 – 125T 220 V / 3 Ph 40 A ~28 A Standard connection
HBM 160/3200 – 160T 220–380 V / 3 Ph 63 A ~45 A Stable 3-phase required
HBM 200/4000 – 200T 380–480 V / 3 Ph 80 A ~60 A Industrial supply
HBM 250/6000 – 250T 480 V / 3 Ph 100 A ~75 A Heavy-duty line
HBM 400–600T 480 V / 3 Ph 125 A+ Crane and 3–4 techs required

5. Required Accessories (Available from UmproTech)

Accessory Description Purpose Typical Price
Step-Up Transformer Converts 220 V → 480 V Required for 200T+ machines $1,200+
Voltage Stabilizer Prevents voltage drop/spike Recommended $280
Frequency Converter Converts 1 Ph → 3 Ph For limited facilities $950+
Hydraulic Oil (ISO VG46) Clean, anti-wear oil For oil fill $85 / 5 gal
Safety Light Curtain Kit Optional safety upgrade Per OSHA standards $250
Crowning Calibration Tool Used during alignment Precision verification $300

6. Installation Timeline

Step Task Typical Duration
1 Unloading and rigging 3–6 hours
2 Machine alignment and leveling 1 day
3 Electrical and hydraulic connections 1 day
4 Pressure calibration and crowning test 0.5 day
5 Controller setup (Delem / ESA) and training 1 day
Total 2–3 days average

7. Non-Compliance & Standby Charges

If the site is not ready at the scheduled time:

  • Standby rate: $120 / hour / technician (min. 2 hours).
  • Rescheduling fee: $600 / day / technician + travel costs.
  • Cancellations < 5 business days: 50% of labor + travel.
  • Unsafe or inaccessible site → work suspended until corrected.

8. Warranty and Support

Standard installation includes 30 days of free remote technical support.

Note: Warranty is void if the machine is relocated, rewired, or operated before official commissioning.

9. Client Responsibilities & Liability

The Client acknowledges responsibility for:

  • Site readiness, utilities, and rigging.
  • Providing hydraulic oil and electrical connection.
  • Covering costs for delays, standby, or re-visits caused by unpreparedness.
  • Safety and compliance at the worksite.
Note: UmproTech technicians reserve the right to halt installation if unsafe or non-compliant conditions are found.

10. Signatures

Role Client Representative UmproTech Engineer
Name
Signature
Date
Installation Address
Contact / Phone

11. Client Responsibility Acknowledgment

By signing below, the Client confirms that all site preparations have been completed according to UmproTech's technical requirements and agrees to all terms, responsibilities, and charges stated in this Agreement.

Client Signature
Date
Company

Contact Information

UmproTech Inc.

901 E Orchard St Unit G, Mundelein, IL 60060

📞 (872) 268-5842 | 📧 am@umpro-tech.com | 🌐 www.umprotech.com

Share Your Review